Project Description

Hazelett Machine

Corporation

Colchester, VT

Pre-engineered steel manufacturing addition, 35,000sf with bridge crane connecting to existing crane way.

Delivery Method:  Negotiated Design-Build

Completed:  June 2001

Owner:  Hazelette Machine Corp.

Design:  E.F. Wall Design-Build

Unique Attributes:  E. F. Wall worked with client personnel in maximizing value for the project during the pre-construction phase.  To minimize impacts to ongoing operations, the construction phase was expedited and compressed to two months form commencement to substantial completion.

 